F3
Office of the President
TO MEMBERS OF THE FINANCE AND CAPITAL STRATEGIES COMMITTEE:
ACTION ITEM
For Meeting of July 17, 2024
SEGUNDO INFILL STUDENT HOUSING, DAVIS CAMPUS: BUDGET, SCOPE,
EXTERNAL FINANCING, AND DESIGN FOLLOWING CONSIDERATION OF AN
ADDENDUM TO THE 2018 LONG RANGE DEVELOPMENT PLAN
ENVIRONMENTAL IMPACT REPORT PURSUANT TO THE CALIFORNIA
ENVIRONMENTAL QUALITY ACT
EXECUTIVE SUMMARY
The Segundo Infill Student Housing project is approximately 116,000 gross square feet in size
and provides 206 new residence hall units targeted for first-year students. The project helps UC
Davis meet the demand for on-campus housing and make progress toward the 2018 Long Range
Development Plan goals and Memorandum of Understanding commitments with the City of
Davis. The project will utilize existing dining and community facilities, given its adjacency to
other residential complexes and available capacity for those amenities, making it a cost-efficient
project. Students who have the benefit of living on campus are immersed in the campus
community with easy access to the variety of academic, research, clinical, recreational, and retail
facilities UC Davis offers, which promotes student success. Providing on-campus housing is
especially beneficial in supporting UC Davis’s underrepresented student groups.
Consistent with the campus’s commitment to responsible stewardship of resources and
demonstrating leadership in sustainable business practices, the project targets a Leadership in
Energy and Environmental Design™ (LEED) minimum building certification level of Gold
with a goal to achieve Platinum.
In May 2023, the Regents approved $4.1 million of preliminary plans funding for the project
from housing reserves.
The Regents are being asked to: (1) approve the project budget of $100,047,000; (2) approve the
project scope; (3) approve external financing in the amount of $98,297,000; (4) adopt the
California Environmental Quality Act Findings; and (5) approve the project design.
FINANCE AND CAPITAL STRATEGIES -2- F3
COMMITTEE
July 17, 2024
RECOMMENDATION
The President of the University recommends that the Finance and Capital Strategies Committee
recommend to the Regents that:
A. The 2024-25 Budget for Capital Improvements and the Capital Improvement Program be
amended as follows:
From: Davis: Segundo Infill Student Housing – preliminary plans – $4.1 million to be
funded from housing reserves.
To: Davis: Segundo Infill Student Housing – preliminary plans, working drawings,
construction, and equipment – $100,047,000 to be funded from external financing
($98,297,000) and housing reserves ($1.75 million).
B. The scope of the Segundo Infill Student Housing project be approved. The project shall
provide a five-story building of approximately 116,000 gross square feet. The building
will house approximately 494 student residents in 206 rooms and will include community
and support spaces with outdoor amenities.
C. The President be authorized to obtain external financing in an amount not to exceed
$98,297,000 plus additional related financing costs to finance the Segundo Infill Student
Housing project and declare that external financing may be used to reimburse prior
expenditures. The President shall require that:
(1) Interest only, based on the amount drawn, shall be paid on the outstanding
balance during the construction period.
(2) As long as the debt is outstanding, the general revenues of the Davis campus shall
be maintained in amounts sufficient to pay the debt service and to meet the related
requirements of the authorized financing.
(3) The general credit of the Regents shall not be pledged.
(4) Any reimbursements will meet all requirements set forth in Treasury Regulations
Section 1.150-2.
D. Following review and consideration of the environmental consequences of the Segundo
Infill Student Housing project, as required by the California Environmental Quality Act
(CEQA), including any written information addressing this item received by the Office of
the Secretary and Chief of Staff to the Regents no less than 48 hours in advance of the
beginning of the Regents meeting, testimony or written materials presented to the
Regents during the scheduled public comment period, and the item presentation, the
Regents:
FINANCE AND CAPITAL STRATEGIES -3- F3
COMMITTEE
July 17, 2024
(1) Adopt the CEQA Findings for the Segundo Infill Student Housing project, having
considered both the 2018 Long Range Development Plan (LRDP) Environmental
Impact Report (EIR) for the Davis campus and June 2024 Addendum to the 2018
LRDP EIR.
(2) Make a condition of approval the implementation of applicable mitigation
measures within the responsibility and jurisdiction of the Davis campus as
identified in the Mitigation Monitoring and Reporting Program adopted in
connection with the 2018 LRDP EIR.
(3) Approve the design of the Segundo Infill Student Housing project, Davis
campus.
BACKGROUND
Past Regents Items
Preliminary Plans, May 2023, $4.1 million (housing reserves).
The project scope remains consistent with that presented to the Regents in May 2023.
Project Background and Context
The UC Davis Student Housing and Dining Services program delivers an excellent on-campus
living experience by providing a safe and comfortable environment that fosters community
interaction and educational development.
As of fall 2023, on-campus housing is available for 15,479 undergraduate and graduate students
in a combination of Regents-owned complexes (6,391 beds) and third party-developed
apartments (9,088 beds). UC Davis currently offers a one-year housing guarantee to incoming
first-year students and a two-year guarantee for incoming transfer students. The campus’s
longstanding goal is to house first-year students in residence hall complexes with programs and
services geared toward supporting students’ academic success and individual development as
they transition to campus life. Although the campus consistently expanded its residence hall
portfolio over the last decade, most recently with the replacement and expansion of Shasta Hall
in 2021 (formerly Emerson Hall), additional residence hall beds are projected to be necessary to
keep pace with anticipated freshmen enrollment growth.
Housing on the Davis campus is organized in several neighborhoods. Traditional residence halls
are located in the Tercero, Segundo, and Cuarto neighborhoods and primarily serve first- and
some second-year students. On-campus apartment-style housing in the Orchard Park and West
Village neighborhoods provides housing primarily to upper-division undergraduates, graduate
students, and student families.
FINANCE AND CAPITAL STRATEGIES -4- F3
COMMITTEE
July 17, 2024
The Segundo neighborhood consists of 14 residence hall buildings, the Segundo Services Center,
and the Segundo Dining Commons, and is located on the northwest corner of the central campus.
The neighborhood’s westside has a park-like setting defined by a north-south axis that connects
community support buildings with open spaces and residence halls. This infill project will
advance the coherence and interconnectedness of the neighborhood.
In addition to increasing residence hall bed inventory in support of enrollment growth, the
additional space will also allow for surge space as the campus anticipates redeveloping old
housing. The project will also continue to move UC Davis towards the goal of housing 48
percent of the Davis campus-based enrollment. As of the 2022-23 academic year, UC Davis
housed 37 percent of Davis-based students on campus.
PROJECT DESCRIPTION
The proposed approximately 116,000-gross-square-foot (gsf) project will provide 206 rooms.
The units primarily support double occupancy but are designed to support tripling to
accommodate fluctuations in enrollment, student demand, and surge space and to provide a lower
cost housing option. The planned configuration upon opening of the project is 60 percent double-
occupancy (124 rooms) and 40 percent triple-occupancy (82 rooms). The units and their design
are generally consistent with those of other well-liked first-year residential neighborhoods at UC
Davis, Cuarto and Tercero. The Segundo Dining Commons will serve the project and will
leverage the full capacity of the dining hall. Other student-serving amenities are available in the
neighborhood; the proximate Segundo Services Center provides administrative and recreational
residential area services, including a service desk, academic advising, computer center,
convenience store, recreation room, and meeting and study rooms. The project is anticipated to
be completed prior to the start of the fall quarter in 2027.
Program and Scope
The building program includes approximately 494 student beds in 206 rooms, communal
bathrooms, two Resident Director Apartments, residential amenities, building amenities, and
building support spaces. Table 1 shows the breakdown of the unit mix, which is designed to
accommodate future shifts in occupancy between double- and triple-bedded rooms based on
future demand factors.
Table 1
Segundo Infill Student Housing Mix of Unit Types
Unit Type
Number
of Units
Number
of Beds
Single Occupancy
0
0
Double Occupancy
124
248
Triple Occupancy
82
246
Total
206
494
FINANCE AND CAPITAL STRATEGIES -5- F3
COMMITTEE
July 17, 2024
Indoor community amenities include floor lounges, study nooks, and convenient laundry
facilities. The ground floor includes a welcoming entry lobby connected to a vibrant main lounge
and a bustling social kitchen. The residential floors maintain a variety of views of the exterior
from nooks, corridors, and lounges, supplementing the connection to the exterior from individual
rooms. Table 2 provides a breakdown of the planned building program.
Table 2
Segundo Infill Student Housing Summary of Proposed Square Footages
Category
ASF
GSF
Residential Space (excluding restrooms)
47,362
Community Amenities
12,857
Restrooms
11,276
Support Spaces
3,843
Total Enclosed Assignable Square Feet (ASF)
75,338
Mechanical Electrical Plumbing
3,852
Covered Unenclosed Area (50%)
4,300
Structure
32,632
Total Project Gross Square Feet (GSF)
116,122
Outdoor Community Amenities
The project creates distinct outdoor social spaces. Pathways are strategically designed to
integrate with the existing multimodal passageways in the neighborhood. The East Entry Plaza
creates an open space to support the extension of indoor programs. The Bicycle Courtyard
includes 600 total bike parking spaces; over 50 percent will be covered by the second-story
podium above, and 25 percent will be enclosed and secured. The landscape, including the Pocket
Park and West Lawn, supports and weaves together open spaces and activities.
Off-Campus Housing Demand
The project will deliver a product that is inherently different from the apartment-style and single-
family homes available in the City of Davis. As a traditional residence hall, the project will
provide additional programming and a board (cafeteria-style meal) program unavailable in the
off-campus market. Increasing the number of residence hall beds on campus assures the campus
that it can uphold its first-year housing guarantee while alleviating some of the challenges the
City of Davis is experiencing with the availability of affordable off-campus housing.
On-Campus Housing Rates and Off-Campus Rent Comparison
The on-campus residential rental rates for singles, doubles, and triples are the same across all on-
campus residential neighborhoods. The socialization of the housing rates ensures those students
living in newer housing units are not burdened with higher rates. The campus’s rates for the
2023-24 academic year are $12,498 per person for a double occupancy room. Although it is too
FINANCE AND CAPITAL STRATEGIES -6- F3
COMMITTEE
July 17, 2024
early to establish rents for FY 2027-28, UC Davis has a long-standing practice of offering below-
market rents and plans to continue this commitment when Segundo Infill is added to the
campus’s housing portfolio.
The following chart notes that rental rates for on-campus housing were nearly 30 percent below
the off-campus Davis market for 2023-24.
Location
2023-24 Monthly Rent
% Under Market
UC Davis Residence Hall Rate,
double occupancy room
$1,180 per person
28%
Davis Community Market Rate,
double occupancy room
$1,650 per person
Notes:
(1) The 2023-24 cost of a double occupancy residence hall was $12,498 per person for the 9.5-month
term, or $1,315 per month. The following on-campus services and amenities have been removed
from the monthly rate in the chart above since these are not provided in off-campus rentals: residence
hall program ($80/month/bed) and utilities ($55/month/bed).
(2) UC Davis residence halls include furnished dorm rooms and housekeeping of common areas. Costs
for these have not been removed from the rate comparison.
(3) Off-campus rates are for unfurnished apartments without Wi-Fi and housekeeping of common areas.
(4) Double occupancy rates are used for both on-and off-campus bedrooms.
(5) Comparison uses two-bedroom, bed lease average data for new construction comparable apartments
in Davis.
Funding Plan and Financial Feasibility
The total project budget of $100,047,000 will be funded with $1.75 million of housing reserves
and $98,297,000 of external financing. At the tax-exempt planning rate of 4.25 percent and
assuming a 30-year term with two years of interest only, the average annual debt service for
years one and two is anticipated to be $4.2 million, and for years three through 30 is anticipated
to be $6.1 million.
Over a ten-year period, the campus is projected to have a minimum modified cash flow margin
of 7.3 percent and a debt service coverage of 1.5x as required by the University’s Debt Policy
(Policy). UC Davis’s days’ cash on hand in the Short Term Investment Pool (STIP)/Total Return
Investment Pool (TRIP) is 62 days as of April 30, 2024, which does not meet the requirements of
the Policy.
The Segundo Infill Student Housing project meets the minimum 1.0x auxiliary project debt
service coverage ratio; however, the campus falls short of the minimum 1.1x auxiliary system
debt service coverage as required by the Policy in the current fiscal year (2024-25). The UC
Davis housing system is projected to meet this requirement in fiscal year 2024-25 and for the
remaining ten-year forecast. An exception to the University’s Debt Policy has been granted by
the Executive Vice President Chief Financial Officer for dayscash on hand and auxiliary
FINANCE AND CAPITAL STRATEGIES -7- F3
COMMITTEE
July 17, 2024
system debt service coverage. Additional information regarding funding and financial feasibility
is included in Attachment 2.
Project Delivery and Schedule
The proposed project is intended to be constructed using the design-build delivery method, with
a Maximum Acceptance Cost, a method successfully employed by UC Davis on a number of
recent housing projects. In this process, the University contracts with a single party for both
design and construction. The design-build process is efficient and allows the contractor’s
technical expertise and creativity to be incorporated into the design process from the beginning.
The design-build process has proven so successful in controlling costs, managing schedules, and
maximizing value for housing projects that the campus now prefers to deliver all-new residence
hall housing projects using this method.
The estimated construction completion date for the project is April 2027.
PROJECT DESIGN
Site Conditions and Location
The proposed project will be located on the existing surface Parking Lots 22 and 16, as shown in
Attachment 4. The location provides convenient access to Russell Boulevard, a main Unitrans
Bus route that connects to the City of Davis; California Avenue, a central street that connects to
the heart of the campus; and Russell Field, which supports campus recreation and events.
The site currently provides parking for the Segundo neighborhood. Much of the construction will
occur on Parking Lot 22, while Parking Lot 16 serves as the laydown site for construction trailers
and temporary facilities. Upon project completion, Parking Lot 16 will continue to serve as a
small surface parking lot for the Segundo neighborhood, with several improvements and
modifications, including relocating the entrance, adding a drop-off and turnaround area,
improving the loading zone, and installing electric vehicle smart chargers. Parking in the
neighborhood is currently undersubscribed, and the first-year residents of the new Segundo Infill
Housing project will not have vehicles, resulting in the ability to continue to meet neighborhood
parking demands even with less parking in the neighborhood. A large parking structure with
capacity to support the displaced parking is located proximate to the neighborhood.
Project Design and Physical Design Framework
The scale of the Project’s five-story structure integrates with the existing two- and three-story
residence hall buildings in the neighborhood and establishes context for future higher-density
development/redevelopment in the neighborhood. The student housing program fosters
community and connection to the main campus, within the Segundo neighborhood, and
throughout the new complex itself.
FINANCE AND CAPITAL STRATEGIES -8- F3
COMMITTEE
July 17, 2024
The main entrance consists of a lobby adjacent to the main corridor on the ground floor of the
building. The west entrance will be adjacent to the Segundo Quad, Segundo Dining Commons,
and the Student Services building to give students traveling from the west side of campus easy
access to the building.
From the Segundo Quad to the west, the project site is organized into four distinct yet
complementary outdoor use zones: the Pocket Park, West Lawn, Bicycle Courtyard, and the East
Entry Plaza. All spaces are interconnected through a permeable ground floor design, which
connects interior and exterior community spaces, providing flexibility and access for students.
The Pocket Park serves as the hub for outdoor space and pedestrian connectivity to the
campus while providing flexible outdoor gathering and studying space.
The West Lawn provides an outdoor amenity for neighborhood residents and
complements a larger open space to the west of the project site.
A Bicycle Courtyard celebrates the campuss vibrant bicycle culture by centralizing the
bike parking facilities. The Bicycle Courtyard includes 600 total bike parking spaces;
over 50 percent will be covered by the second-story podium above and 25 percent will
be enclosed and secured.
The East Entry Plaza provides a point of entry for the facility adjacent to the main
vehicular drop-off zone.
The design of the building and the materials selected are consistent with the campus’s Physical
Design Framework. The public outdoor spaces have been carefully designed to promote the
connection between buildings and landscaping. The design and materials selected promote a
cohesive environment in the Segundo Neighborhood through consistency of scale, color, and
textures while ensuring longevity and maintainability. Exterior finishes will include brick,
exterior insulation and finishing system panels, aluminum windows, and concrete site surfaces.
A materials sample is included with the design materials in Attachment 5.
Sustainable Practices
The building will achieve a minimum Leadership in Energy and Environmental Design™
(LEED) Gold certification, with the goal of Platinum. The entire project will incorporate
electrification and will not utilize natural gas for building heat or hot water generation.
Additionally, the building will have:
Operable windows
High-performance exterior envelope design
Low-emitting materials
Daylighting
High-quality views
Lighting controls
Durable materials
Reduction of indoor water use to exemplary levels
Outdoor bicycle parking
FINANCE AND CAPITAL STRATEGIES -9- F3
COMMITTEE
July 17, 2024
Long Range Development Plan (LRDP)
The project is consistent with the 2018 LRDP. The 2018 LRDP land use designations for the site
are Student Housing and Streetscapes and Roadways. The Student Housing designation allows
for a variety of campus and privately operated student housing types and densities and includes
ancillary services to support housing (i.e., landscape, path, on-site utility services, and parking).
Beckett Hall Circle will be widened from a multimodal path to provide full emergency vehicular
access around the new building, which is consistent with its current use. The project will develop
student housing at the site and increase the on-campus residential population; therefore, the
Segundo Student Infill Housing project is consistent with the 2018 LRDP.
CONSISTENCY WITH SELECT UC POLICIES AND PRACTICE
The project complies with the UC Policies for Seismic Safety, Sustainability, and Small/Disabled
Veteran Business Enterprises (see Attachment 7).
CEQA COMPLIANCE
Pursuant to the California Environmental Quality Act (CEQA), a June 2024 Addendum to the
2018 LRDP EIR (SCH# 2017012008) has been prepared for the Segundo Infill Student Housing
Project (Attachment 9). The Project is within the scope of impacts identified and analyzed in the
2018 LRDP EIR, and none of the circumstances that will trigger subsequent or supplemental
environmental review under Public Resources Code Section 21166 and CEQA Guidelines
Sections 15162 or 15163 have occurred or are present. With the implementation of relevant
certified 2018 LRDP EIR mitigation measures, no new significant environmental impacts have
been identified in connection with the revised Project that were not considered in the 2018 LRDP
EIR. The 2018 LRDP EIR Mitigation Monitoring program is applicable to the project, and
applicable mitigation measures for the Project can be found in Section 5 of the June 2024
Addendum. Findings have been prepared to support the University’s determination that the
proposed project will not require major revisions to the 2018 LRDP EIR (Attachment 11).
Key to Acronyms
CEQA
California Environmental Quality Act
EIR
Environmental Impact Report
gsf
Gross Square Feet
LEED
Leadership in Energy and Environmental Design™
LRDP
Long Range Development Plan
Policy
University’s Debt Policy
STIP
Short Term Investment Pool
TRIP
Total Return Investment Pool
FINANCE AND CAPITAL STRATEGIES -10- F3
COMMITTEE
July 17, 2024
ATTACHMENTS:
Attachment 1:
Project Sources and Uses
Attachment 2:
Summary of Financial Feasibility
Attachment 3:
Comparable Project Information – Scatterplot and Table
Attachment 4:
Project Location Map/Site Map
Attachment 5:
Design Graphics
Attachment 6:
Alternatives Considered
Attachment 7:
Statement of UC Policy Compliance
Attachment 8:
2018 LRDP:
https://ucdavis.app.box.com/s/3b7029z14i9j8n2nr2vfcnejl8kbs71h
Attachment 9:
June 2024 Addendum to the 2018 LRDP EIR:
https://ucdavis.app.box.com/v/SegundoInfillHousing-Addendum
Attachment 10:
2018 LRDP EIR and Mitigation Monitoring and Reporting Program:
https://ucdavis.app.box.com/s/yqhq0ni1f7ce1mhpqux61g9oqfs326ow
Attachment 11: CEQA Findings
Attachment 12:
UC Operational Carbon and Energy Assessment for New Construction
(OCEAN) Tool
ATTACHMENT 1
PROJECT SOURCES AND USES
SEGUNDO INFILL STUDENT HOUSING
PROJECT SOURCES
Source
Total
Percent of
Total
Housing Reserves
$1,750,000
1.7%
External Financing
$98,297,000
98.3%
Total Sources
$100,047,000
100%
PROJECT USES
Use
Total
Percent of
Total
Site Clearance
$3,751,000
4.0%
Building
$62,292,000
66.9%
Exterior Utilities
$3,977,000
4.3%
Site Development
$3,790,000
4.1%
A/E Fees
1
$2,173,000
2.3%
Campus Administration
2
$5,990,000
6.4%
Surveys, Test, Plans
$602,000
0.6%
Special Items
3
$6,996,000
7.5%
Contingency
$3,581,000
3.8%
P-W-C Cost
4
$93,152,000
100%
Group 2 & 3 Equipment
$1,750,000
Project Total
$94,902,000
Interest During Construction
$5,145,000
Grand Total
$100,047,000
1
A/E fees include the executive architect/engineer’s basic services contract fee.
2
Campus Administration includes project management and inspection.
3
Special Items include: detailed project program and other pre-design study consultants, environmental services consultants, plan check fees,
major local jurisdiction fees, special design consultants, independent structural /seismic and MEP review, hazardous materials
abatement/remediation design services, and commissioning agent.
4 Cost of preliminary plans (P), working drawings (W), and construction (C).
PROJECT STATISTICS
Gross-Square-Foot (GSF)
116,122
Assignable-Square-Foot (ASF)
75,338
Efficiency Ratio ASF/GSF
64.9%
Building Cost/ASF
$827
Building Cost/GSF
$536
P-W-C Cost/ASF
$1,236
P-W-C Cost/GSF
$802
Building Cost/Unit
$302,388
Building Cost/Bed
$126,097
P-W-C Cost/Unit
$452,194
P-W-C Cost/Bed
$188,567
Cost Drivers
The Design Build delivery method maximizes value in a few distinct ways:
The Design Build process locks in a Maximum Allowable Cost (MAC) early in the
design phase, providing cost certainty and eliminating the risks related to rising inflation
and / or long lead times for procurement.
In addition, having the contractor as part of the design team ensures that costs are
considered at every stage of the design process. This approach provides maximum
alignment of campus priorities and design outcomes, resulting in maximum value to the
campus.
By having a single contract with both the Architect and Contractor, the design-build
partner assumes the risks associated with errors and omissions from the design team. In a
Design-Bid-Build model, the University would be responsible for architectural errors and
omissions. The Design Build method provides a substantial benefit to the University in
this regard.
By reducing redundancy in the design process, the Design Build method often speeds up
project durations by up to 12 percent, resulting in cost savings for both the design-build
partner and the University.
ATTACHMENT 2
SUMMARY OF FINANCIAL FEASIBILITY
DAVIS CAMPUS
Project Name
Segundo Infill Student Housing
Project ID
953200
Total Estimated Project Cost
$100,047,000
Anticipated Interest During Construction
(included in total estimated project cost)
$5,145,000
PROPOSED SOURCES OF FUNDING
Housing Reserves
$1,750,000
External Financing
$98,297,000
Total
$100,047,000
Below are results of the financial feasibility analysis for the proposed project using the campus’s Debt
Affordability Model. The model includes projections of the campus’s operations and planned financings.
CAMPUS FINANCING BENCHMARKS
Measure
Campus Metric
Approval Threshold
Requirement
Modified Cash Flow
Margin
7.32% (minimum),
2026
≥ 0.0%
Must Meet
Debt Service Coverage 1.5x (minimum), 2025 ≥ 1.1x
STIP/TRIP Days Cash on
Hand*
62 days, 04/30/2024 ≥ 90 days
Auxiliary Project Debt
Service Coverage
1.03x (minimum),
2030
≥ 1.0x
Must Meet for
Auxiliary Projects
Auxiliary System Debt
Service Coverage*
0.92x (minimum),
2024
≥ 1.1x
*Metric does not meet the requirements of the University’s Debt Policy. [The Executive Vice PresidentChief
Financial Officer has granted an exception to the Policy.]
FINANCING ASSUMPTIONS
External Financing Amount
$98,297,000
Anticipated Repayment Source
General Revenues of the Davis campus
Anticipated Fund Source
Davis Housing Revenues
Financial Feasibility Rate
4.25%
First Year of Principal (e.g. FY 20XX)
2027 (two years interest only 2027-2028)
Term (e.g. 30 years)
30 years
Final Maturity (e.g. FY 20XX)
2056
Estimated Average Annual Debt Service
$4,178,000 (2027-2028)
$6,070,000 (2029-2056)
ATTACHMENT 6
ALTERNATIVES CONSIDERED
As the initial phase of redevelopment of student housing in the Segundo neighborhood, the
housing site for the Segundo Infill Student Housing project and the number of beds necessary to
develop to meet the needs of the Davis Student Housing Master Plan helped determine the scope
of the project. Prior to proceeding with campus-delivered new development, the campus
considered several delivery alternatives to provide this additional housing capacity and to
achieve housing capacity, quality, and program goals in alignment with the objectives outlined
above.
Evaluation Criteria
All project alternatives comply with the campus plans outlined in the Long Range Development
Plan. The primary criteria for selecting the project alternate include meeting the campus’ need
for additional beds in a financially feasible manner. It is also desired that the Segundo Infill
Student Housing development integrate with the existing Segundo neighborhood.
Alternative 1—a renovation project.
This alternative will renovate buildings within either Primero Grove or Regan Hall, which will
address building systems and provide a general renewal of the facilities; however, it will not
provide significant additional capacity beyond the existing beds; therefore, it is not a viable
alternative. If Alternative 1 was pursued, there would be a significant cost; however, the campus
would not gain additional on-campus student beds, and the overall design of the space and
neighborhood would not be improved.
Alternative 2—replacement of an entire residential facility.
This alternative will demolish existing housing in the Segundo Neighborhood and replace it with
new construction. The new construction option allows for the site to be configured to integrate
from a site planning and architectural perspective with the previous phases of development in the
Segundo Neighborhood and for the expansion of the number of beds provided in the resulting
facility to include approximately 400 to 600 additional beds, meeting the campus’ demonstrated
needs for additional beds. This alternative allows for the maximization of energy efficiency,
increased density, and better community integration of single beds. However, this will result in a
loss of beds while the project is underway, displacing students from being able to live on
campus.
Alternative 3new construction.
This alternative will construct a new residence hall as an infill project to the existing Segundo
Neighborhood. The new construction option provides the same benefits listed above in
Alternative 2 without the displacement of on-campus student residents during the projects
construction.
Analysis of these alternatives concluded that Alternative 3 is the preferred option. This is the
only option that will allow the campus to meet all identified goals for housing at this site and on
campus. The new residence hall beds, along with ancillary support services to support residents
within the Segundo Infill Student Housing and the larger Segundo Neighborhood, will be
constructed on the parking lot sites between Primero Grove and Regan Hall.
Alternative 4Public-Private Partnership delivery.
The campus also evaluated a fourth alternative, the construction of a new facility through a
Public-Private Partnership (P3) delivery. P3s at the University of California can be structured in
a variety of transaction forms, including:
Ground Lease-Leasebacks, in which a Regents-owned site is ground leased to a private
developer who builds the project and leases the facilities back to UC.
Developer Build-to-Suit, in which a developer builds the project on either private or
Regents-owned land and, upon completion, purchases it from UC.
The developer builds and operates the facility on Regents-owned land through a ground
lease.
Under the right circumstances, P3s have the potential to offer savings in time, reduce the
expenditure of capital reserves, and preserve the campus’ debt capacity. Consideration of P3s by
UC is based primarily on potential advantages in risk allocation and management efficiencies
offered by experienced private developers who specialize in building types commonly developed
by the private sector. The campus has determined that Segundo Infill Student Housing is not a
suitable candidate for a P3 development because:
Revenue Streams and Financial Feasibility:
While a P3 could minimize the campus’ initial capital outlay, the campus will forgo a
substantial income stream in the long term.
The resulting income stream will be used to fund other aspects of the housing program,
such as program enrichment and reserves. A percentage of this funding stream will also
go toward campus programs and infrastructure. The housing rates are socialized to keep
costs as low as possible for students.
A P3 provides no advantage to the campus with regard to “risk” allocation or debt limit.
“Risk” of vacancy and subsequent default is considered low due to the limited amounts of
on-campus housing at UC Davis.
Residential Life:
A significant element of the project is the residential program experience, student services, and
programs to support the successful transition of first-year and transfer students into campus life.
The campus has significant expertise in delivering student life programs that include tutoring,
counseling, recreation, and other support services. For first-year students, the targeted population
for additional housing in the Segundo neighborhood, the campus’ own experience with P3-
developed housing indicates that privatizing student life program delivery to these students is not
as successful as programs managed by the Davis campus professionals. A P3-developed housing
facility in this neighborhood will be challenging to seamlessly integrate with the student
experience throughout the existing first-year housing neighborhood.
Delivery and Operating Efficiencies:
Campus staff has significant experience in developing student housing. Since 2004, the
campus has successfully managed the construction of nearly 4,000 student beds. The
most recent campus-delivered housing project was the Emerson Hall Replacement
project, which opened in fall 2021. The project demolished a 50-year old building and
built a denser residential building, adding approximately 300 beds to the campus
inventory.
Segundo Infill Student Housing will have operating synergies with Primero Grove, Regan
Hall, and the Segundo Dining Commons, all of which are operated by UC Davis Student
Housing and Dining Services.
Recommendation
The campus has determined that Alternative 3a campus-delivered and managed new
construction project providing approximately 400 to 600 beds—is the highest-value project for
the campus. The project addresses the primary evaluation criteria for capacity and leverages the
neighborhood’s existing amenities and support services for operational efficiencies. The project
also enhances the residential community and provides critical flex space for the University to
maintain its overall housing inventory.
ATTACHMENT 7
STATEMENT OF UC POLICY COMPLIANCE
The project is consistent with selected UC Policies and Practices:
Sustainable Practices Policy
This project will comply with the University of California Sustainable Practices Policy. The
Sustainable Practices Policy establishes goals for green building, clean energy, transportation,
climate protection, facilities operations, zero waste, procurement, food service, and water
systems. A full range of sustainability practices for building design and operations is included in
the budgeting, programming, and design effort for the project.
Small Business Enterprises (SBEs) and Disabled Veteran Business Enterprises (DVBEs)
The campus is committed to promoting and increasing participation of Small Business
Enterprises (SBEs) and Disabled Veteran Business Enterprises (DVBEs) in all purchasing and
contract business, subject to any applicable obligations under State and federal law, collective
bargaining agreements, and University policies. The campus regularly communicates with
interested contractors and consultants to provide information about how to find opportunities to
work at the campus and to encourage them to respond to the annual announcement soliciting
interest to perform services. Providing qualified SBEs with the maximum opportunity to
participate will be encouraged with the selected design professionals and contractors with the
goal of meeting 25 percent participation.
Seismic Safety
This project will comply with the University of California Seismic Safety Policy, including
independent seismic peer review.