Department
of Public Service
NYSERD
A
FACT SHEET
NEW YORK STATE’S PROCESS FOR CONSIDERING SITES FOR WIND FARMS
Wind power is clean, renewable energy. In New York State, all power sources, including
wind farms, that generate more than 25 megawatts (MW) are considered power plants.
For example, a 25-MW wind farm can generate roughly the electric power needed for
8,000 average households.
Major electric generating facilities larger than 25 MW are sited according to New
York State’s Article 10 law. This comprehensive law provides precise guidance to
the New York State Board on Electric Generation Siting and the Environment (Siting
Board) about authorizing construction and operation of major electric generating
facilities, including wind farms. The Article 10 law streamlines the application process
for developers, while providing a rigorous process for local input and ensuring
environmental and public health laws are followed.
*
Developers apply to the Siting Board for a Certificate of Environmental Compatibility
and Public Need that authorizes them to build and operate a wind farm. The Siting
Board reviews applications and information from communities and other interested
parties, and then issues or denies certificates.
A transparent and open process
The Siting Board consists of five permanent members (the heads of five state agencies.
NYS PSC, NYSERDA, DEC, DOH and ESD) and two public members drawn from the
community, who provide a local voice in the proceeding. Local ocials submit a list of
candidates, and two public members are selected from that list.
The public can participate in the decision-making process by oering support; voicing
concerns; or asking questions about public health, safety, the environment, or other
factors. This proactive process begins during the initial planning of the facility and
continues throughout the siting review, construction, and operation.
Step 1: Public Involvement Program
Developers must implement public involvement programs in the respective
communities at least 150 days before submitting their preliminary scoping statement
and ocial applications to the Siting Board.
Developers should conduct public outreach before any agreements are made
between the developer and interested parties. The program includes:
Fostering the active, early, and continuing involvement of interested or
aected persons.
Providing for an open exchange of information and ideas between
community members and the developer.
Providing timely notice to community members of important events.
• Soliciting local expertise.
Identifying circumstances that may not have been known or anticipated
by the developer or government agencies.
Step 1:
Public Involvement Program
Public Involvement Program
must be submitted for review
at least 150 days prior to the
submittal of any preliminary
scoping statement.
Step 2:
Preliminary Scoping Statement
Public Involvement Program
and Preliminary Scoping
Statement must be approved
before developer can
submit a formal application.
The Preliminary Scoping
Statement must be filed no
less than 90 days before
filing a formal application.
Step 3:
Formal Application
Siting Board has 60 days
to assess if the formal
application complies with
the Article 10 law. Then
public hearings can be
scheduled.
Step 4:
Siting Board Decision
Siting Board conducts a
formal hearing and must
make a final decision to
issue or deny a certificate
within 12 months of when
the developer’s application
was deemed complete.
Article 10 Process
* The Siting Board must determine that the wind farm will comply with all state and local laws regarding the environment, public health and safety.
The Siting Board may decide not to apply local laws that are deemed unreasonably burdensome or costly to ratepayers. Local laws are generally
presumed to be valid and should only be found unreasonably burdensome after fully considering evidence submitted by the municipality.
Specific ways that developers can interact with communities
may include:
Communicating with community members early in
the public involvement part of the process by various
means such as media coverage, direct mailings, fliers,
or newsletters.
Holding public meetings and giving presentations to
individual groups and organizations.
Establishing a presence in the community such as a
local oce, a toll-free telephone number, website, or a
community advisory group.
Step 2: Preliminary Scoping Statement
The preliminary scoping statement is a written document
informing the Siting Board, other public agencies, and the
community about the project, including a description of
the proposed facility, potential environmental and health
impacts, proposed studies to evaluate those impacts,
proposed mitigation measures and reasonable alternatives
to the project.
Both the public involvement program and preliminary
scoping statement will be reviewed by Department of Public
Service sta, who may oer recommendations for revisions
and additional information to improve the documents. The
developer may consider these recommendations in revising
and resubmitting the public involvement program and
the preliminary scoping statement. Once the preliminary
scoping statement is filed, the developer must submit a fee
to be used for intervenor funding during the pre-application
phase. These funds may be used by local governments and
other stakeholders to hire experts to review and propose
revisions to the preliminary scoping statement. The two
local members of the Siting Board are appointed at this time,
and the Administrative Law Judge assigned to the case will
convene a public meeting.
Step 3: Formal Application
After the public involvement program and preliminary scoping
statement are filed, developers must then submit a formal
Article 10 application to the Siting Board, which includes
the same information as the preliminary scoping statement
but in greater detail. The Siting Board has 60 days after the
application is submitted to determine whether it complies with
the requirements of the law, regulations, and stipulations.
If the application does not comply with the requirements, the
Siting Board will issue a letter to the developer advising of the
deficiencies that must be corrected before the application will
be considered complete.
If the application is complete, the Siting Board will set the
date for the commencement of its public hearings and the
Department of Environmental Conservation will initiate
its review pursuant to federally delegated or approved
environmental permitting authority for air and water permits.
Intervenor Fees. To encourage community and stakeholder
participation, developers who apply are assessed an
intervenor fee equal to $1,000 for each 1 MW of generating
capacity of the subject facility, but no more than $400,000.
For example, for a 100-MW facility, the intervenor fee for the
application would be $100,000. These fees are in addition to
fees paid during the preliminary scoping statement phase.
Municipal and local governments and other parties to the
proceeding are eligible to apply to receive intervenor funds.
These funds can be used to defray expenses incurred by
municipal and local parties for expenses such as expert
witnesses, consultants, administrative costs (document
preparation and duplication costs), and legal fees.
Hearings. The application review process will include both
public statement hearings and trial-type hearings to give
community members and stakeholders opportunities to
fully participate.
Step 4: Siting Board Decision
The Siting Board must make its final decision about whether
to issue or deny the certificate within 12 months of the
date that a developers application is deemed complete. In
extraordinary circumstances, the Siting Board may extend
the deadline by no more than six months to consider specific
issues. In order to approve the certificate, the Siting Board
must make a finding that the requirements of Article 10 have
been fully met.
LSR-LGW-siting-fs-1-v1 7/16
Department
of Public Service
NYSERD
A
For more information
Read the details of Article 10: www.dps.ny.gov/article10law
Contact James Denn, Public Information Coordinator, Department of Public Service
Email: james.denn@dps.ny.gov
Phone: 518.474.7080